Sea Dragon

 

Gordon Engineering was awarded the contract in October of 2008 to supply 2 helifuel packages, tanks and tank lay down skids.

TRANSOCEAN RICHARDSON

Gordon Engineering travelled to the installation off the coast of Angola. The system was inspected and found to be in a poor condition. After consulting the Rigs management team the decision was made to fully replace and upgrade the package.

 

A new delivery and pump package were manufactured and delivered to the installation on schedule.

 

The old system was made safe and removed. The new package was laid down in the original designated areas. A new 1" Pneumatic line was installed as the new motor was air driven.

 

New 2" Stainless steel pipe was fitted to accommondate the new systems specification.

 

The system was fully tested and commissioned by Gordon Engineering.

 

Onboard crew completed the Gordon Engineering training Module.